Key Procedure Starts Pertaining to Actual Start of Construction of Gas Interconnector with Greece

Key Procedure Starts Pertaining to Actual Start of Construction of Gas Interconnector with Greece

Sofia, April 30 (BTA) - ICGB AD, the project company developing the Gas Interconnector Greece-Bulgaria, has announced a public procurement procedure for the design, delivery and construction of the facility, the company said on Monday.

The projected value of the public procurement is 145 million euro pre-VAT. The term is 18 month after the start of the construction works.

The selection procedure is in two stages: preliminary selection, and assessment and ranking of the bids of the pre-selected candidates.

In the preliminary selection ICGB will select the bidders having the requisite financial and technical capacity to carry out the works.

Source: Sofia